Meeting called to order at 6:30 pm.


Roll Call: Present: Julie Hager, Harvey Sothmann, Shannon Craigmiles, Della Rogers

Scott, Pat Fidlar. Absent: Alvin Barber was working on a main break. Also present: Steve

Haring (MSA), Shelley Strombach, Bob VanHooreweghe, Darci Toppert (BHBT), Toni

Gasper (BHBT), Linda Meinheit, Tom Ray, Sarah Ford (Review), Deputy B. Mendoza

(RICS), John Myers.

MSA: MSA presented an updated project report to let the board know they are close to

completion on the Nano2 system. They anticipate it will be able to be switched on within

the month. MSA has not received any bids for the Shamrock Villa’s storm grate work.

The Survey performed at 3rd Ave & 9th Street N & 10th Street North is complete. The

Village has copies of the paperwork.

MidAmerica: MidAmerica presented the information for their LED programs. They

have two options. Option 1: The Standard Conversion- the customer agrees to allow

MEC (at no cost to the Customer) to begin converting existing MEC-owned HPS and

other non-LED street lights with a comparable LED street light fixture by project areas as

planned by MEC and at MEC’s discretion and pace. Option 2: Accelerated ConversionThe

Customer request that HPS and other non-LED street lights (in the locations

designated in writing by the Customer) be converted to LED fixtures prior to such light’s

planned conversion by MEC and significant maintenance on the light is required (e.g., on

a faster pace and timeline than under Option 1). There will be a charge of $100.00/light

for each conversion that occurs under Option 2. An MEC representative will contact the

Customer (through primary point of contact for the Customer identified below) to

document the locations desired by the Customer for early conversion under Option 2 and

to begin working on the process to identify and change the streetlights. The LED lights

are predicted to last 10 years after installation. The LED lights are simply a head

replacement on the existing fixtures. MidAmerica projected an estimated $2000.00 yearly

savings for Cordova’s current number of lights. The lights have better visibility and the

lights are more directional. It is a whiter light. Jim signed the paperwork to start the

Village on Option 1 with the knowledge the Village could later switch to Option 2.

Black Hawk Bank & Trust: Black Hawk Bank & Trust offered a packet full of

information for the Board outlining what they can offer the Village. They have a full

range of options for businesses. The Board will go through the information and discuss.

Water/Sewer: The Nano2 system’s generator will need money put into it this coming

week. The Village will have to send out a part to be welded as it is a stainless steel item.

The snowbird policy will be retracted and the Village will re-write a policy for water and

sewer usage.

Park & Rec: The mowing is slowing down now with the weather change. The Village

will need to rent a skid loader with attachment to go in and start clearing brush around

town. The skid loader is $350/day or $1100 for the week.

S&A: Della will need money approved for purchasing road signs as well as some road

repair where the main break occurred. The Slurry Sealcoating project has had 2

contractors respond.

Finance: Shannon gave everyone a copy of the Budget worksheet that shows the current

expenses versus budget for the months ending in July.

Waste Management: Fall Cleanup will be October 6th, 7th, & 8th at the Civic Center

building. The 7th the Village will be hosting E-waste at the Village Hall maintenance

building from 9am-12pm. The Board will also need to decide on a price for extra garbage

cans for citizens who wish to have one.

Donation: The Cordova Fire Protection District is requesting a donation for their

Pancake Breakfast October 1st. There will be food, games, crafts, and fun for the whole

family from 7am-1pm. The Cordova Boosters have also requested a donation for their

Halloween Party. The planning for the Halloween Party will determine where the party

and times are.

Public Comments: Jim apologized for the road messes we have had recently. Jim also

let everyone know he has had a meeting with McClure engineering about the survey they

are conducting for the property located behind the Village Maintenance buildings and the

Fire Department. They are having issues with two pieces of property by the railroad, they

expect to be completed by the end of October.

Pat made a motion to adjourn, Shannon 2nd, 5 ayes

Meeting adjourned at 7:19 pm.

https://img1.wsimg.com/blobby/go/b19c8f92-b62b-4e5c-b484-c0a26ba9af85/downloads/1br2iqrpc_852088.pdf

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate